Its going to cost the City of Kenora a bit more money to complete the submarine waterline project between Water Street and Norman.
The two million dollar project will replace the existing waterline and will eventually connect up to Coney Island and the new condodevelopment on Tunnel Island.
Councillor Dave McCann says the extra work will mean an additional 76 thousand dollars for the contract.
He says they also agreed to allow the contract to work seven days a week to complete the project by October 1st.